Project Status

11/13/2017

Interstate Impacts:   I-95 Median and Drainage Work on West Side of Bridge.   I-95 Bridge over the West River Concrete Deck and Parapet Pours.   Paving of I-95 Median Area on East Side of Bridge.   I-95 Bridge Over Ella Grasso Boulevard Parapet Pours  
Local Road/Sea Street Impacts:   Ella Grasso Boulevard Roadway Work Beginning in November 2017.   Roadway Work Resuming in the Spring of 2018.   Kimberly Avenue Roadway Work Resuming in the Spring of 2018.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

10/30/2017

Interstate Impacts:   I-95 Bridge over the West River Concrete Deck and Parapet Pours.  
Paving of I-95 Median Area Starting the Week of October 30, 2017.  
Sea Street Impacts:   Roadway Work Resuming in the Spring of 2018.  
Local Road Impacts:   Ella Grasso Boulevard Roadway Work Beginning in Mid-November 2017.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

10/02/2017

Sea Street Impacts:   Roadway Work Resuming the week of October 16, 2017.  
Local Road Impacts:   Ella Grasso Boulevard Roadway Work Beginning the Week of October 2, 2017.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

09/18/2017

Interstate Impacts:   I-95 Southbound Lane Closures on Wednesday, September 20, 2017, for pouring of concrete deck on Bridge No. 163 at night.  
Sea Street Impacts:   Roadway Work Resuming at the End of September 2017.  
Local Road Impacts:   Ella Grasso Boulevard Roadway Work Beginning the Week of September 18, 2017.   Lining of Sanitary Sewer Work on Greenwich Avenue to take Place During the Week of September 18, 2017.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

08/21/2017

Interstate Impacts:   I-95 Southbound Lane Closures for Metal Beam Rail Repair and Survey Work at Night.  
Sea Street Impacts:   Roadway Work Resuming Towards End of September 2017.  
Local Road Impacts:   Deck Work for Bridge No. 163 Over Kimberly Avenue, Including Deck Pans, Studs and Reinforcing.>   I-95 Median Barrier and Drainage.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

07/24/2017

Interstate Impacts:   I-95 Northbound and Southbound Lane Closures for Median Construction and Drainage Work at Night.  
Sea Street Impacts:   Roadway Work Resuming at the Beginning of August 2017.  
Local Road Impacts:   I-95 Median Roadway and Electrical Work.   Work on Mitigation Area off Compost Road.   Jacking of Stage 3 Structural Steel for Bridge No. 163.   Deck Work for Bridge No. 163 Over Kimberly Avenue
View photos for this phase |  View the Bi-Weekly Project Update Flyer

06/12/2017

Interstate Impacts:   Repair of Metal Beam Rail and Potholes on I-95 NB and SB at Night.  
Sea Street Impacts:   Installation of new driveways at CT DOT Maintenance Facility and Greenwich Avenue.   Excavation and grading along north side of Sea Street.  
Local Road Impacts:   I-95 Median Roadway and Electrical Work.   Pouring Concrete for the Substructures of New Bridge No. 163 over the West River.   Removal of Portions of the Temporary Work Trestle for Bridge No. 163.   Work on Mitigation Area off Compost Road.   Jacking of Stage 3 Structural Steel for Bridge No. 163. This will involve Kimberly Ave. detour the week of June 19, 2017 between the hours of 6:00 p.m. and 6:00 a.m.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

05/29/2017

Sea Street Impacts:   Installation of new driveways at CT DOT Maintenance Facility and Greenwich Avenue.   Excavation and grading along north side of Sea Street  
Local Road Impacts:   I-95 Median Roadway and Electrical Work.   Pouring Concrete for the Substructures of New Bridge No. 163 over the West River.   Removal of Portions of the Temporary Work Trestle for Bridge No. 163.   Work on Mitigation Area off Compost Road.   Hauling and Unloading of Stage 3 Structural Steel
View photos for this phase |  View the Bi-Weekly Project Update Flyer

04/15/2017

Sea Street Impacts:   Installation of new driveway at CT DOT Maintenance Facility  
Local Road Impacts:   I-95 Median Roadway and Electrical Work.   Pouring Concrete for the Substructures of New Bridge No. 163 over the West River.   Removal of Portions of the Temporary Work Trestle for Bridge No. 163.   Begin work on Mitigation Area off Compost Road.   Demolition of Existing Bridge No. 163 Substructure
View photos for this phase |  View the Bi-Weekly Project Update Flyer

04/03/2017

Sea Street Impacts:   U.I. pole relocation work, associated with the traffic calming and roundabout revisions on Sea Street, has been approved by CT DOT and is expected to begin in the near future.  
Local Road Impacts:   Installation of Piles and Pouring Concrete for the Substructures of New Bridge No. 163 over the West River.   Removal of Portions of the Temporary Work Trestle for Bridge No. 163.   Pouring Concrete for the Deck of Bridge No. 164 over Ella Grasso Boulevard.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

03/20/2017

Work associated with the traffic calming and roundabout revisions on Sea Street will begin in March 2017, starting with the removal of trees and shrubs between the CTDOT Maintenance Building driveway and Greenwich Avenue.   Installation of Piles and Pouring Concrete for the Footings of New Bridge No. 163 over the West River.   Installation and Grading of Fill between Bridge Nos. 163 and 164.   Installation of Deck Reinforcing and Shear Studs for Bridge No. 164 over Ella Grasso Boulevard.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

03/06/2017

Work associated with the traffic calming and roundabout revisions on Sea Street will begin in March 2017, starting with the removal of trees and shrubs between the CTDOT Maintenance Building driveway and Greenwich Avenue.   Installation of Piles and Pouring Concrete for the Footings of New Bridge No. 163 over the West River.   Installation and Grading of Fill between Bridge Nos. 163 and 164.   Installation of Stay-in-Place Deck Forms and Overhang Brackets for Bridge No. 164 over Ella Grasso Boulevard.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

10/03/2016

Lane Closures on I-95 SB will be required to complete the roadway maintenance and Contract work on Thursday night, October 6, 2016 and on Wednesday night, October 12, 2016.   The I-95 SB on-ramp from Ella Grasso Boulevard at Interchange 44 will be closed from 9:00 p.m. on Wednesday night, October 12, 2016, to 6:00 a.m. on Thursday morning, October 13, 2016.   Continue the temporary realignment of the on-ramp from Ella Grasso Boulevard to I-95 SB at Interchange 44.   Begin reconstruction of Kimberly Avenue.   Begin demolition of existing Stage 3 bridge over Ella Grasso Boulevard.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

09/06/2016

Lane Closures on both I-95 NB and SB will be required to complete the Stage 3 superstructure demolition of the I-95 bridge over the West River.   Work is scheduled to start on Monday night, September 12, 2016 and is expected to last approximately three weeks.   Begin the temporary realignment of the on-ramp from Ella Grasso Boulevard to I-95 SB at Interchange 44.   Daytime activities that may create vibrations and/or noise are scheduled to occur throughout the period from Tuesday, September 6 to Saturday, September 17, 2016.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

07/11/2016

Right lane closure on I-95 SB between Exits 46 and 43 on Friday night, July 15, 2016, for roadway work associated with the opening of the new ramp from Ella T. Grasso Boulevard to I-95 SB. See attached CTDOT Press Release.  Construction of parapets for new I-95 SB Stage 2 Bridge over Ella T. Grasso Boulevard.  Roadway work for new I-95 SB Exit 44 ramp to Ella T. Grasso Boulevard.  Roadway work on new I-95 SB approaches to Bridge No. 164 over Ella T. Grasso Boulevard and Bridge No. 163 over the West River.
View photos for this phase |  View the Bi-Weekly Project Update Flyer |  View the CTDOT Press Release

06/20/2016

Roadway and drainage work on I-95 SB between Exits 43 and 44 from Thursday night, June 23, 2016, to Thursday night, June 30, 2016.  Bridge deck work for new I-95 SB Stage 2 Bridge over Ella T. Grasso Boulevard.  Membrane waterproofing and paving of new I-95 SB Stage 2 Bridge over the West River.  Daytime activities that may create vibrations and/or noise are scheduled to occur throughout the period from Monday, June 20, 2016 to Saturday, July 2, 2016.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

05/23/2016

Emergency work on I-95 SB to repair two settlement areas on Thursday night, June 2, 2016.  Pouring concrete for foundations of new Bridge No. 164 over Ella T. Grasso Boulevard.  Pouring concrete for Bridge No. 163 Stage 2 parapets and approach slabs.  Roadway and drainage work on I-95 on-ramp from Ella T. Grasso Boulevard at Interchange 44. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

05/02/2016

Installation of piles and pouring concrete for foundations of new Bridge No. 164 over Ella T. Grasso Boulevard.  Drainage and roadway work on Ella T. Grasso Boulevard.  Pouring concrete for Bridge No. 163 Stage 2 deck.  Roadway work on I-95 on-ramp from Ella T. Grasso Boulevard at Interchange 44. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

03/28/2016

Installation of piles for foundation of new Bridge No. 164 over Ella T. Grasso Boulevard.  Steel erection for new Bridge No. 163 over the West River.   Drainage and roadway work on Ella T. Grasso Boulevard. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

03/14/2016

Demolition of the existing I-95 SB Bridge over the West River from 5:00 p.m. to 2:30 a.m.  Pouring concrete for substructures of new Bridge No. 163 over the West River.  Installation of piles for foundation of new Bridge No. 164 over Ella T. Grasso Boulevard.  Steel erection for new Bridge No. 163 over the West River. Detour on Kimberly Avenue from 6 p.m. to 6 a.m. on March 15, 2016 and March 16, 2016 for this operation. See attached Press Release.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

02/15/2016

Demolition of the existing I-95 SB Bridge over the West River from 5:00 p.m. to 2:30 a.m.  Pouring concrete for substructures of new Bridge No. 163 over the West River.  Support of excavation and demolition for the new I-95 bridge over Ella T. Grasso Boulevard.  Installation of piles for foundation of new bridge No. 163 Ella T. Grasso Boulevard.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

01/18/2016

Demolition of the existing I-95 SB Bridge over the West River from 5:00 p.m. to 2:30 a.m.  Installation of piles for foundations of new Bridge No. 163 over the West River. Pile installation will continue through January 2016 between the hours of 6:30 a.m. and 6:00 p.m.  Pouring concrete for substructures of new Bridge No. 163 over the West River.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

12/28/2015

Demolition of the existing I-95 SB Bridge over the West River from 5:00 p.m. to 1:30 a.m. starting January 11, 2016.  Installation of piles for foundations of new Bridge No. 163 over the West River. Pile installation will continue through mid - January 2016 between the hours of 6:30 a.m. and 6:00 p.m.  Pouring concrete for substructures of new Bridge No. 163 over the West River.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

11/23/2015

Construction of noise wall along I-95 southbound, Exit 44 Ramp.  Demolition of the existing I-95 SB Bridge over the West River.  Installation of piles for foundations of new Bridge No. 163 over the West River.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

10/26/2015

Construction of Wall 101 along I-95 southbound, Exit 44 Ramp.  Demolition of the existing I-95 SB Bridge over the West River.  Installation of speed tables, signs and pavement markings on Sea Street, from 9 PM Friday night, October 30, 2015, to 10 AM Saturday morning, October 31, 2015. Expect alternating one-way traffic during this time period.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

09/14/2015

Demolition of existing I-95 southbound bridges over the West River and Ella Grasso Boulevard.  Pouring of concrete for Wall 101 along I-95 southbound, Exit 44 Ramp.  Installation of drainage along Ella Grasso Boulevard.  Installation of temporary stage 2 trestle over the West River.  New on-ramp alignment from Ella Grasso Boulevard to I-95 southbound.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

08/17/2015

A major traffic shift on I-95 southbound is scheduled for Friday night, August 28, 2015 to Monday morning, August 31, 2015 in the towns of New Haven and West Haven.  Nightly I-95 southbound lane closures for traffic shift prep work.  Pouring of concrete for Wall 101 along I-95 southbound, Exit 44 Ramp.  Construction of temporary ramp from Ella Grasso Boulevard to I-95 southbound.  Removal of Stage 1 temporary trestle and installation of temporary Stage 2 trestle over the West River.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

07/20/2015

Pouring of concrete for wall 101 along I-95 SB Exit 44 exit ramp.  Demolition of permanently closed I-95 SB Exit 44 loop ramp.  Construction of the I-95 NB Bridge over Ella Grasso Boulevard and its approaches.  Construction of temporary ramp from Ella Grasso Boulevard to I-95 SB.  Removal of Stage 1 temporary trestle and installation of temporary Stage 2 trestle over the West River. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

07/06/2015

Pouring of concrete for wall 101 along I-95 SB Exit 44 exit ramp.  Demolition of permanently closed I-95 SB Exit 44 loop ramp.  Pouring of concrete for the parapet of the I-95 NB Bridge over Ella Grasso Boulevard.  Construction of temporary wire wall support systems along I-95 NB and I-95 NB Exit 44.  Removal of Stage 1 temporary trestle and installation of temporary Stage 2 trestle over the West River. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

06/22/2015

Demolition of permanently closed I-95 SB Exit 44 loop ramp.  Pouring of concrete for the substructures and deck of the I-95 NB Bridge over Ella Grasso Boulevard.  Construction of temporary wire wall support systems along I-95 NB and I-95 NB Exit 44.  Removal of Stage 1 temporary trestle and installation of temporary Stage 2 trestle over the West River.  Continue installation of noise barrier wall along I-95 NB in the vicinity of the I-95 entrance ramp from Ella Grasso Boulevard. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

06/08/2015

Removal of preload material along I-95 SB Exit 44 ramp.  Demolition of permanently closed I-95 SB Exit 44 loop ramp.  Pouring of concrete for the structures of the I-95 NB Bridge over Ella Grasso Boulevard.  Construction of temporary wire wall support systems along I-95 NB and I-95 NB Exit 44.  Removal of Stage 1 temporary trestle over the West River  Installation of the structural steel for the I-95 NB Bridge over Ella Grasso Boulevard at night on June 10, 2015 and June 11, 2015. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

05/25/2015

Paving on Ella Grasso Boulevard and I-95 NB Exit 44 ramp.  Begin demolition of permanently closed I-95 SB Exit 44 loop ramp.  Kimberly Avenue roadway reconstruction.  Pouring of concrete for the abutments of the I-95 NB Bridge over Ella Grasso Boulevard.  Construction of temporary wire wall support systems along I-95 NB and I-95 NB Exit 44. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

05/11/2015

Begin demolition of permanently closed I-95 SB Exit 44 loop ramp.  Pouring of the concrete deck and approach slabs for new bridge over the West River.  Kimberly Avenue roadway reconstruction.  Pouring of concrete for the abutments of the I-95 NB Bridge over Ella Grasso Boulevard. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

04/27/2015

Begin demolition of permanently closed I-95 SB Exit 44 loop ramp.  Installation of the noise barrier wall along the new on-ramp from Ella Grasso Boulevard to I-95 NB.  Installation of piles for the new I-95 NB Bridge over Ella Grasso Boulevard.  Pouring of the concrete deck for new bridge over the West River.  Kimberly Avenue roadway reconstruction.  Installation of drainage along Ella Grasso Boulevard Extension. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

04/13/2015

Night work on I-95 NB and SB is scheduled from Friday, April 17, 2015 through Friday, April 24, 2015 from 9 PM to 6 AM for various operations, including the installation of new overhead signs.  Permanent closure of I-95 SB Exit 44 ramp to Kimberly Ave.  Installation of the noise barrier wall along the new on-ramp from Ella Grasso Boulevard to I-95 NB.  Installation of piles for the new I-95 NB Bridge over Ella Grasso Boulevard.  Pouring of the concrete deck for new bridge over the West River.  Construction of additional lane for Ella Grasso Boulevard Extension to Kimberly Avenue.  Realignment of the I-95 NB Exit 44 off ramp to Kimberly Avenue. 
Starting April 21, 2015 the I-95 SB Exit 44 loop ramp will be permanently closed. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

03/16/2015

Installation of the noise barrier wall along the new on-ramp from Ella Grasso Boulevard to I-95 NB.  Excavation and demolition of substructure of existing I-95 NB Bridge over Ella Grasso Boulevard and installation of piles for the new bridge.  Installation of drainage on Ella Grasso Boulevard.  Installation of deck pans for new bridge over the West River.  Construction of temporary Ramp "A" for I-95 NB. 
Starting April 21, 2015 the I-95 SB Exit 44 loop ramp will be closed.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

03/02/2015

Installation of the noise barrier wall along the new on-ramp from Ella Grasso Boulevard to I-95 NB.  Excavation and demolition of structure of existing I-95 NB Bridge over Ella Grasso Boulevard.  Installation of drainage on Ella Grasso Boulevard.  Setting of structural steel for new bridge over the West River. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

02/16/2015

Forming, installing reinforcement and pouring concrete  Forming, installing reinforcement and pouring concrete for the substructures of Bridge No. 163 over the West River.  Installation of the noise barrier wall along the new on-ramp from Ella Grasso Boulevard to I-95 NB.  Excavation and demolition of substructure of existing I-95 NB Bridge over Ella Grasso Boulevard.  Installation of drainage on Ella Grasso Boulevard.  Setting of structural steel for new bridge over the West River. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

02/02/2015

Forming, installing reinforcement and pouring concrete for the substructures of Bridge No. 163 over the West River.  Installation of the noise barrier wall along the new on-ramp from Ella Grasso Boulevard to I-95 NB.  Excavation and demolition of structure of existing I-95 NB Bridge over Ella Grasso Boulevard. Installation of drainage on Ella Grasso Boulevard.  Installation of girders for I-95 NB Bridge. This includes night work for the span over Kimberly Avenue scheduled for the nights of Tuesday, February 3, 2015 through Wednesday, February 4, 2015, with associated maintenance and protection of traffic. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

01/19/2015

Forming, installing reinforcement and pouring concrete for the substructures of Bridge No. 163 over the West River.  Installation of the noise barrier wall along the new on-ramp from Ella Grasso Boulevard to I-95 NB.  Excavation and demolition of structure of existing I-95 NB Bridge over Ella Grasso Boulevard. Installation of drainage on Ella Grasso Boulevard.  Installation of girders for I-95 NB bridge. This includes night work for the span over Kimberly Avenue scheduled for the nights of January 26, 2015 through January 29, 2015, with associated maintenance and protection of traffic. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

01/05/2015

Forming, installing reinforcement and pouring concrete for the substructures of Bridge No. 163 over the West River.  Installation of the noise barrier wall along the new on-ramp from Ella Grasso Boulevard to I-95 NB.  Demolition of I-95 NB Bridge over Ella Grasso Boulevard. Night work is scheduled for January 7, 2015, January 8, 2015 and January 9, 2015 with maintenance and protection of traffic set up on Ella Grasso Boulevard.  Installation of drainage on Ella Grasso Boulevard. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

12/08/2014

Forming, installing reinforcement and pouring concrete for the substructures of Bridge No. 163 over the West River.  Installation of the noise barrier wall along the new on-ramp from Ella Grasso Boulevard to I-95 NB.  Removal of pre-load soil material adjacent to I-95 NB Exit 44 off-ramp. 
Note: Revisions for access to I-95 NB on-ramp from Kimberly Avenue took effect on December 5, 2014. A press release was issued and provides the details.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

11/24/2014

Daytime construction at Sea Street and Ella Grasso Boulevard including drainage, paving and restriping.  Forming, installing reinforcement and pouring concrete for the substructures of Bridge No. 163 over the West River.  Installation of the noise barrier wall along the new on-ramp from Ella Grasso Boulevard to I-95 NB. 
Note: Revisions for access to I-95 NB on-ramp from Kimberly Avenue and Ella T. Grasso Blvd. took effect on November 15, 2014. A press release has been issued and provides the details.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

11/10/2014

Daytime construction at Sea Street, including drainage and restriping.  Forming, installing reinforcement and pouring concrete for the substructures of Bridge No. 163 over the West River.  Ramp "C" construction from Ella Grasso Boulevard to I-95 NB, including grading, drainage, sign installation, paving and illumination. 
Note: Revisions for access to I-95 NB on-ramp from Kimberly Avenue and Ella T. Grasso Blvd. to take effect on November 21, 2014. A press release has been issued and provides the details.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

10/27/2014

Daytime construction at Ella T. Grasso Boulevard and Sea Street, including drainage.  Daytime work for the installation of preload embankment along I-95 NB Exit 44 off- ramp to Kimberly Avenue.  Forming, installing reinforcement and pouring concrete for the substructures of Bridge No. 163 over the West River.  Ramp “C” construction from Ella Grasso Boulevard to I-95 NB, including grading, drainage and illumination. 
Note: Revisions for access to I-95 NB on-ramp from Kimberly Avenue and Ella T. Grasso Blvd.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

10/13/2014

Daytime construction at Ella T. Grasso Boulevard and Sea Street, including drainage.  Daytime work for the installation of wick drains and preload embankments along I-95 NB Exit 44 off- ramp to Kimberly Avenue and along entrance ramp to I-95 SB from Ella T. Grasso Boulevard.  Daytime work for construction of new Ramp D from I-95 SB to Ella T. Grasso Boulevard.  Daytime work for widening of I-95 SB to Exit 45 shoulder area including paving.  Installation of piles for West River Bridge.  Forming, installing reinforcement and pouring concrete for the substructures of Bridge No, 163 over the West River. 
Note: Revisions for access to I-95 NB on-ramp from Kimberly Avenue and Ella T. Grasso Blvd. to take affect by mid of November 2014. A forthcoming press release will provide details.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

09/29/2014

Daytime construction of Ella T. Grasso Boulevard and Sea Street, including drainage.  Daytime work for the installation of preload embankments along I-95 NB Exit 44 off- ramp to Kimberly Avenue and along entrance ramp to I-95 SB from Ella T. Grasso Boulevard.  Daytime work for excavation of new Ramp D from I-95 SB to Ella T. Grasso Boulevard.  Daytime work for widening of I-95 SB to Exit 45 in shoulder area including paving.  Installation of piles for West River Bridge.  Forming, installing reinforcement and pouring concrete for the substructures of Bridge No, 163 over the West River. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

09/15/2014

Daytime construction of Ella T. Grasso Boulevard and Sea Street, including drainage.  Daytime work for the installation of preload embankments along I-95 NB Exit 44 off- ramp to Kimberly Avenue and along entrance ramp to I-95 SB from Ella T. Grasso Boulevard.  Daytime work for excavation of new Ramp D from I-95 SB to Ella T. Grasso Boulevard.  Daytime work for widening of I-95 SB to Exit 45 in shoulder area including paving.  Installation of piles for West River Bridge.  Forming, installing reinforcement and pouring concrete for the substructures of Bridge No, 163 over the West River. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

09/02/2014

Daytime construction of Ella T. Grasso Boulevard and Sea Street, including drainage.  Daytime work for the installation of preload embankments along I-95 SB Exit 45 off- ramp to Ella T. Grasso Boulevard and along entrance ramp to I-95 SB from Ella T. Grasso Boulevard.  Daytime work for excavation of new Ramp D from I-95 SB to Ella T. Grasso Boulevard.  Daytime work for widening of I-95 SB to Exit 45 in shoulder area.  Installation of piles for West River Bridge. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

08/18/2014

Daytime construction of Ella T. Grasso Boulevard and Sea Street including drainage.  Daytime work for the installation of preload embankments along I-95 SB Exit 45 off- ramp to Ella T. Grasso Boulevard.  Daytime work for excavation of new Ramp C to I-95 NB.  Daytime work for widening of I-95 SB to Exit 45 in shoulder area.  Installation of piles for West River Bridge. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

08/04/2014

Daytime construction of Ella T. Grasso Boulevard and Sea Street.  Daytime work for the installation of preload embankments along I-95 NB between of Exit 44 off- ramp to Kimberly Avenue and Exit 45 on-ramp to I-95 NB.  Installation of piles for West River Bridge. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

07/21/2014

Daytime construction of Ella T. Grasso Boulevard and Sea Street.  Daytime work for the installation of preload embankments along I-95 NB in the area of Exit 44 off- ramp to Kimberly Avenue.  Installation of piles for West River Bridge.  Pave portions of Ella T. Grasso Boulevard and Harborside Trail. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

07/07/2014

Daytime construction of Ella T. Grasso Boulevard and Sea Street.  Daytime removal of sound barrier along I-95 NB in vicinity of Greenwich Ave.  Daytime work for the installation of preload embankments along I-95 NB in the area of Exit 44 off- ramp to Kimberly Avenue.  Construction of temporary earth retaining systems.  Installation of piles for West River Bridge. 
View photos for this phase |  View the Bi-Weekly Project Update Flyer

06/23/2014

Nighttime work on I-95 Northbound and Southbound to facilitate bridge and roadway construction.  NOTE: Effective Friday, June 27, 2014 - No Closures Scheduled on I-95 from 5PM Friday, June 27, through 5AM Monday, June 30, 2014.  Daytime construction of Ella T. Grasso Boulevard and Sea Street.  Daytime construction of I-95 NB on-ramp from Kimberly Avenue.  Daytime work for the installation of preload embankments along I-95 NB in the area of Exit 44 off- ramp to Kimberly Avenue.   Construction of temporary earth retaining systems.  Installation of piles for West River Bridge, Abutment 2.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

06/09/2014

Daytime construction of Ella T. Grasso Boulevard and Sea Street.  Daytime construction of I-95 NB on-ramp from Kimberly Avenue.  Daytime work for the installation of preload embankments along I-95 NB in the area of Exit 44 off- ramp to Kimberly Avenue.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

06/02/2014

Daytime construction of Ella T. Grasso Boulevard and Sea Street.  Daytime construction of I-95 on-ramp from Kimberly Avenue.  Daytime work for the installation of preload embankments along I-95 NB and along I-95 SB Exit 45 ramp between Ella T. Grasso Boulevard and Greenwich Ave.  Preparation of soil solidification area at Kimberly Avenue/I-95 NB entrance ramp at Exit 44.
View photos for this phase |  View the Weekly Project Update Flyer

05/27/2014

Daytime construction of Ella T. Grasso Boulevard and Sea Street.  Daytime work for the installation of preload embankments along I-95 NB and along I-95 SB Exit 45 ramp between Ella T. Grasso Boulevard and Greenwich Ave.  Preparation of soil solidification area at Kimberly Avenue/I-95 NB entrance ramp at Exit 44.
View photos for this phase |  View the Weekly Project Update Flyer

05/19/2014

There will be no interstate impacts on May 23, 2014 and May 26, 2014 (Memorial Day).
Daytime roadway reconstruction on Ella T. Grasso Boulevard and Sea Street.  Daytime work for the installation of preload embankments along I-95 NB and along I-95 SB Exit 45 ramp between Ella T. Grasso Boulevard and Greenwich Ave.  Preparation of soil solidification area at Kimberly Avenue/I-95 NB entrance ramp at Exit 44.
View photos for this phase |  View the Weekly Project Update Flyer

05/05/2014

Daytime preparing for sanitary sewer bypass in the vicinity of I-95 SB Exit 45 ramp and Ella T. Grasso Boulevard intersection. Daytime work for the installation of preload embankments along I-95 NB and along I-95 SB Exit 45 ramp between Ella T. Grasso Boulevard and Greenwich Ave. Preparation of soil solidification area at Kimberly Avenue/I-95 NB entrance ramp at Exit 44.
View photos for this phase |  View the Weekly Project Update Flyer

04/28/2014

Daytime activities for sanitary sewer bypass in the vicinity of I-95 SB Exit 45 ramp and Ella T. Grasso Boulevard intersection. Daytime work for the installation of preload embankments along I-95 NB and along I-95 SB Exit 45 ramp between Ella T. Grasso Boulevard and Greenwich Ave. Preparation of soil solidification area at Kimberly Avenue/I-95 NB entrance ramp at Exit 44. Construction of temporary work trestle over the West River, including driving of pipe piles.
View photos for this phase |  View the Weekly Project Update Flyer

04/21/2014

Daytime preparing for sanitary sewer bypass in the vicinity of I-95 SB Exit 45 ramp and Ella T. Grasso Boulevard intersection. Daytime work for the installation of preload embankments along I-95 NB and along I-95 SB Exit 45 ramp between Ella T. Grasso Boulevard and Greenwich Ave. Preparation of soil solidification area at Kimberly Avenue/I-95 NB entrance ramp at Exit 44.
View the Weekly Project Update Flyer

04/14/2014

Nighttime work on I-95 Northbound and Southbound to facilitate bridge and roadway construction. Daytime preparing for sanitary sewer bypass in the vicinity of I-95 SB Exit 45 ramp and Ella T. Grasso Boulevard intersection. Daytime work for the installation of preload embankments along I-95 NB and along I-95 SB Exit 45 ramp between Ella T. Grasso Boulevard and Greenwich Ave. Daytime and nighttime activities that may create vibrations and/or noise are scheduled to occur throughout the period from Monday, April 7, 2014 through Friday, April 11, 2014.
View the Weekly Project Update Flyer

04/03/2014

Embankment construction for soil preload in progress South of I-95 NB West Haven side. West temporary work trestle beginning, receiving & stockpiling materials. East Trestle installation in progress, first span has been erected pile driving operation continuing. Wick drain installation for soil preload continuing South of I-95 NB between Exit 45 Ramp Areas, in addition to areas near Greenwich Ave & DOT Maintenance Facility.
View photos for this phase |  View the Weekly Project Update Flyer

03/26/2014

Wick drain installation in progress South of I-95 NB in West Haven. Driving piles for the temporary work trestle South of I-95 NB. Clearing areas for soil preload areas South of I-95 in the Exit 45 interchange. Prep work continuing for sanitary sewer bypass.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

03/17/2014

Prep work for sanitary sewer bypass in vicinity of I-95 SB Exit 45 ramp and Ella T. Grasso Boulevard intersection.
View the Bi-Weekly Project Update Flyer

03/04/2014

Middlesex Corporation has continued to mobilize on site, receiving multiple deliveries of equipment and materials every day. Upcoming work on site includes clearing of select trees in preparation for soil preload areas and reconstruction of Exit 45 ramps, placing temporary barges in the West River, and preparing the site for the temporary work trestle.
View photos for this phase |  View the Bi-Weekly Project Update Flyer

01/30/2014

The West River Project has commenced. The contractor, The Middlesex Companies was awarded the contract to replace the Existing I-95 West River Bridge, Ella Grasso Blvd Bridge, and Interchange Improvements to Exit 45. The contractor has begun to mobilize large cranes used to erect work trestles so work can begin for the footings of the new span over the West River.
View photos for this phase